Client:
CWH Construction GmbH
Location // Project:
Austria // Schwechat
Technical parameters:
EXC 3; factory production, delivery and on-site installation of 123 062 kg double-track railway bridge
Client:
Swietelsky Magyarország Kft.
Location // Project:
Kaposvár //Kaposvár IMCS
Technical parameters:
EXC 3; factory production, delivery and on-site installation of 438 265 kg pedestrian and bicycle bridge
Client:
CWH Construction GmbH
Location // Project:
Austria // Marchegg
Technical parameters:
EXC 3; factory production, delivery and on-site installation of 113 121 kg pedestrian and bicycle bridge
Client:
CWH Construction GmbH
Location // Project:
Austria // JANE JACOBS STEG
Technical parameters:
EXC 2; factory production, delivery and on-site installation of 68 540 kg pedestrian and bicycle bridge
Client:
CWH Construction GmbH
Location // Project:
Austria // Münchendorf bridge
Technical parameters:
EXC 2; factory production, delivery and on-site installation of 25 642 kg composite bridge
Client:
TOMOS Kft.
Location // Project:
Budapest, floating dock
Technical parameters:
EXC 2; overall dimensions: 20 x 14.5m, production of 26 870 kg steel structure
Client:
KÉSZ Építő és Szerelő Kft.
Location // Project:
Product design, production and on-site installation of the steel structure and auxiliary structures of Abaújvár – Hernád river // Road bridge
Technical parameters:
EXC 3; overall dimensions: 60 x 11 x 15 m, 151 400 kg steel structure + 87 400 kg auxiliary structure.
Client:
MARKET Zrt.
Location // Project:
Product design, production and on-site installation of steel structures, Gyöngyöshalász
Technical parameters:
EXC 2; production of 128 000 kg steel structure
Client:
ZÁÉV Zrt., ÉPKAR Zrt.
Location // Project:
Product design, production and on-site installation of the steel structures of the hall building, Budapest
Technical parameters:
EXC 3; production of 208 000 kg steel structure
Client:
ZÁÉV Zrt.
Location // Project:
Product design, production and on-site installation of the steel structures of the hall building, Nagykanizsa
Technical parameters:
EXC 3; production of 324 000 kg steel structure
Client:
Lakógép Kft
Location // Project:
Környe, Volta Energy Solutions gyárbővítés. Gép- és csőtartó szerkezet, kapcsolódó lépcső korlát elemekkel.
Üzemi gyártás, szállítás, helyszíni szerelés
Technical parameters:
253.000 kg horganyzott acélszerkezet
Client:
Market Építő Zrt
Location // Project:
LIDL Logisztikai Raktárközpont Ecser, acél és lakatosszerkezetek (cső-, és tetőgéptartó, acélfödémek,
menekülőlépcsők, ütközésvédők) gyártmánytervezése, üzemi gyártása, szállítása és helyszíni szerelése.
Műszaki Paraméterek:
450.000 kg horganyzott acélszerkezet